DeLong Mountain Regional Transportation System (DMTS) Transportation Corridor
| Task Number |
Check |
Tasks |
Date |
Comment |
| 1 |
þ |
Risk Assessment Scoping Meeting |
August 22, 2002 |
DEC Project Manager; DEC Risk Assessment Staff and consultants; Responsible Person (RP); and RP consultants |
| 2 |
þ |
Teck Cominco submits revised Conceptual Site Model (CSM) |
Early Oct.2002 & Mid Dec. 02 |
Identifies all potential exposure. Submitted to DEC project manager. Second revised version submitted Mid-Dec. addressing DEC comments. |
| 3 |
þ |
DEC Approves Conceptual Site Model |
January 22, 2003 |
|
| 4 |
þ |
Teck Cominco submits Draft Work Plan for the Risk Assessment |
January 2003 |
Includes CSM identifying all completed pathways. Submitted to DEC project manager. |
| 5 |
þ |
Public review and comment period on Draft Work Plan, including human health and ecological risk |
Mid-Jan. - late Feb. 2003 |
30-day Public Notice Period during Feb. 03 for comments on the Draft Work Plan, including public meetings |
| 6 |
þ |
DEC works with Teck Cominco to address DEC's concerns and public comments on the risk assessment work plan. |
Mid-March - Dec. 2003 |
To DEC project manager |
| 7 |
þ |
Field sampling: Teck Cominco develops a Sampling Plan to fill in soil and other physical data gaps identified during the work plan process* Data gathered in summer. |
Mid-June 2003 |
DEC approves sampling plan |
| 8 |
þ |
DEC provides comments to Teck Cominco on the draft risk assessment workplan and publishes Responsiveness Summary (PDF 47K) |
December 2003 and early February 2004 |
|
| 9 |
þ |
Teck Cominco submits a revised Risk Assessment Work Plan.
|
Early February 2004 |
|
| 10 |
þ |
DEC provides comments regarding revised Risk Assessment Work Plan (PDF 556K). |
Mid-April 2004 |
|
| 11 |
þ |
DEC approves Sampling Plan and publishes Responsiveness Summary. |
Early June 2004 |
|
| 12 |
þ |
More field sampling:Teck Cominco gathers data on plants and animals. Data collected in summer. |
Early June 2004 |
DEC approves sampling plan |
| 13 |
þ |
Teck Cominco submits final response to DEC revised Risk Assessment Work Plan comments. |
Mid-September 2004 |
|
| 14 |
þ |
Comment resolution meeting. Discussions on-going between DEC and Teck Cominco. |
Mid-April to early October 2004 |
|
| 15 |
þ |
DEC approves revised Risk Assessment Work Plan and publishes Responsiveness Summary (response to comments on draft) |
October 20, 2004 |
For the revised risk assessment work plan |
| 16 |
þ |
DEC Reviews draft Risk Assessment report |
September 8, 2005 |
Comments provided to RP after a public notice period, April 12 - July 11, for comments on the draft Risk Assessment Report |
| 17 |
þ |
Teck Cominco Submits response to DEC Risk Assessment Comments |
November 10, 2005 to June 28, 2007 |
To DEC project manager |
| 18 |
þ |
Comment Resolution Meeting |
June 29 to October 30, 2007 |
For the risk assessment draft Report |
| 19 |
þ |
DEC Approves the Risk Assessment Report |
December 19, 2007 |
For the risk assessment final Report |
| 20 |
o |
DEC Makes Risk Management Decision and Approves Alternative Cleanup Levels, Remedial Action, or No Further Action |
TBD |
|
*Some tasks may occur concurrently
**TBD = To be determined |