Shoreline Cleanup Assessment : Pre-inspection Endpoint Assessment and Final Inspections
With completion of the initial SCAT survey, the SCAT teams have been renamed the Pre-inspection Endpoint Status assessment Team (PEST) and are conducting helo-supported post-treatment inspections of segments prior to landowner inspections. The PEST teams verify that cleanup operations were successful in achieving the established cleanup criteria. If additional cleanup is deemed necessary, the team will recommend appropriate additional measures. State and Federal field monitors, together with contractor cleanup managers meet with the teams during inspections to insure discrepancies are corrected. A final inspection team of Unified Command and landowner representatives will then visit each cleaned segment and forward their recommendations to the Unified Command for consideration towards final UC approval of the cleanup on that segment.

Shoreline Cleanup Assessment Technique (SCAT) Program Spring/Summer 2005 (PDF 2.52 MB)

SCAT Recommended Treatment Maps

Status
All SCAT surveys of the 806 shoreline segments were completed on June 16, 2005. Based on additional shoreline inspections and a review of safety issues, the UC approved 21 segments to be removed from treatment consideration when the assessment teams found the segments met endpoint criteria and/or the segments had access and safety concerns. This leaves a total of 102 segments approved by the UC to be treated.

Status of the segments surveyed at the end of the SCAT team operations

Total Segments 806 (469 miles, 763 km)
Total Segments Surveyed 806 (100% of total)
Segments no treatment or no further treatment 681 (90% of total, 423 miles, 649 km)
Segments requiring treatment 123 (15% of total, 70 miles, 113 km)
Segments approved by UC for treatment 102 (13% of total) Length of actual oiled shoreline 19.9 miles, 32.2 km

Progress Towards UC Approval of Cleanup Completion (through July 13, 2005)
Total segments requiring treatment (STRTs) 102
Segments treated and submitted for pre-inspection 62
Total segments pre-inspected and approved for final inspection 58
Total segments ready for final inspection 54
Total segments passing final inspection 3
Total segments signed off by Unified Command 0

Progress Maps: through August 9, 2005: