Wastewater Discharge Authorization
DEC Watermark logo  
 

SWPPP Submittal Requirements

1.1 The permittee must submit a copy of the SWPPP to ADEC for review (to ADEC, Wastewater Discharge Authorization – Storm Water, 555 Cordova St, Anchorage, AK 99501) if the project is located outside the areas of the local governments described in Sections 1.2, 1.3, 1.4, and 1.5 and the project disturbs five or more acres of land;

1.2 Within the Municipality of Anchorage

1.2.1 An owner or operator of construction projects disturbing one or more acres of land shall submit a copy of the SWPPP to either ADEC or the Municipality based on the project type and operator as shown in the following table

Project Type Submit SWPPP to
Government (federal, state, municipal) road projects and other government transportation projects such as ports, railroads or airports ADEC
Utility projects for which the utility is initiating the work Municipality
Work that requires a Building Permit Municipality
Non-publicly funded transportation projects Municipality
1.2.2 Submittal of the SWPPP to the Municipality should be made before or at the same time the NOI is submitted to ADEC and shall be accompanied by any Municipality-required fee. A copy of the SWPPP shall be submitted to the Municipality at the following address:

Steve Ellis
Municipality of Anchorage
Office of Planning Development and Public Works
4700 South Elmore Rd.
PO Box 196650
Anchorage, AK 99519-6650
343-8078
EllisSM@muni.org


1.2.3 Submittals to ADEC shall include a copy of the SWPPP for review.

1.3 Within the urbanized area boundary of the Fairbanks North Star Borough check with the Borough for the latest requirements.

Jennifer Schmetzer
Fairbanks North Star Borough
Department of Public Works
PO Box 71267
Fairbanks, AK 99707
459-1327
jschmetzer@co.fairbanks.ak.us


1.4 Within the urbanized area boundary of the City of Fairbanks

1.4.1 Owners or operators of privately-funded construction projects disturbing one or more acres of land shall submit a copy of the SWPPP to the City of Fairbanks.

1.4.2 Submittal of the SWPPP to the City of Fairbanks should be made before or at the same time the NOI is submitted to ADEC and shall be accompanied by any City-required fee. A copy of the SWPPP shall be submitted to the City of Fairbanks at the following address:

Jackson Fox
City of Fairbanks
Engineering Division
800 Cushman St
Fairbanks, AK 99701
459-6758
jcfox@ci.fairbanks.ak.us


1.4.3 Owners or operators of publicly-funded projects disturbing one or more acres of land shall submit a copy of the SWPPP to ADEC for review.

1.5 Within the urbanized area boundary of the City of North Pole

1.5.1 Owners or operators of privately-funded construction projects disturbing one or more acres of land shall submit a copy of the SWPPP to the City of North Pole.

1.5.2 Submittal of the SWPPP to the City of North Pole should be made before or at the same time the NOI is submitted to ADEC and shall be accompanied by any City-required fee. A copy of the SWPPP shall be submitted to the City of North Pole at the following address:

Bill Butler
City of North Pole
Department of Public Works
125 Snowman Lane
North Pole, AK 99705
bill@northpolealaska.com


1.5.3 Owners or operators of publicly-funded projects disturbing one or more acres of land shall submit a copy of the SWPPP to ADEC for review.

 

 